| April 2009 |
Olin and design team begin schematic design phase |
| May 2009 |
Construction begins on interim clearing and planting. New sod and grass will be planted so that the community can enjoy the area while the Park’s design is completed. |
| June 2009 |
Interim clearing and planting completed. |
| December 2009 |
100% Schematic Design complete |
| February 2010 |
100% Design Development complete |
| June 2010 |
100% Construction Documentation complete |
| August 2010 |
Construction on adjacent street infrastructure begins |
| September 2010 |
Construction on Park begins |
| October 2011 |
Park opens |